2 Budget Composition

  Main Estimates
30/6/08
$000
Supp. Estimates
30/6/08
$000
Budget
Total
30/6/08
$000
Income
Revenue Crown 62,793 (4,367) 58,426
Revenue other 52,140 1,676 53,816
Total income 114,933 (2,691) 112,242
Expenditure
Personnel costs 42,347 3,452 45,799
Depreciation and amortisation 13,086 (2,583) 10,503
Capital charge 2,956 2,956
Restructuring costs
Other operating expenses 70,107 (1,222) 68,885
Total expenditure 128,496 (353) 128,143
Net surplus/(deficit) (13,563) (2,338) (15,901)

Explanations of major changes in the Supplementary Estimates:

Revenue Crown

The decrease in revenue Crown was mainly from transfers of funding to later years, partly off-set by the carry-forward of expense transfers of funding for strategic projects from 2006/07.

Revenue other

The increase in revenue other was due to an upward revision of third-party revenue from survey and title transactions.

Personnel costs

The increase reflects funding for the 100% electronic lodgement Cabinet decision.

Depreciation and amortisation

The decrease reflects capital expenditure occuring later than originally expected.

Other operating costs

The decrease reflects funding for projects carried forward to 2008/09.