Note: this guideline is issued by the Surveyor-General under section 7(1)(ga) of the Cadastral Survey Act 2002 about the Rules for Cadastral Survey 2010 and is not legally binding.

This article relates to the information required in a CSD under rule 8 in addition to that required in either the CSD Plan or the Title Plan under rules 9 and 10.

The additional information is required to:

  • allow the CSD to be integrated into the cadastre,
  • enable the tenure manager to issue the intended rights, and
  • ensure future users of the CSD (including future surveyors) understand the evidence and the rationale used by the certifying surveyor when certifying the CSD.

The other specified information includes:

Diagram showing other information in a CSD
Figure 1: Other information in a CSD
Last Updated: 7 April 2017
Authority: Surveyor-General - Section 7(1)(ga) of the Cadastral Survey Act 2002
LINZ OP G : 00065