Note: this guideline is issued by the Surveyor-General under section 7(1)(ga) of the Cadastral Survey Act 2002 about the Rules for Cadastral Survey 2010 and is not legally binding.

The following information relates to the key components that are required in a boundary marking survey office (SO) CSD.

A Title Plan is not required in a SO CSD that only records the placement of a boundary mark [r 8.1(b) and 11.3].  This is because a new parcel is not being created.

Key plan components of an SO CSD recording boundary marking are:

  • A CSD recording boundary marking is required to include only a CSD Plan [r 8.1(b) and 11.3].
  • This CSD plan consists of both diagrammatic and non-diagrammatic information.
  • The diagrammatic information must be depicted on a Diagram of Survey [r 9.6.1 and 11.3(b)(v)].
Figure 1: Components of a CSD recording boundary marking
Last Updated: 4 April 2017
Authority: Surveyor-General - Section 7(1)(ga) of the Cadastral Survey Act 2002
LINZ OP G : 00079