Project timeline

Our work on the project to date.

2016

The Treaty Settlements Landbank is transferred to Toitū Te Whenua management.

2017

Ngāti Maniapoto and the Crown sign the Te Hautahi Agreement in Principle to Settle Historic Claims.

2017 – 2019

Toitū Te Whenua investigate several demolition options and costs.

2019

Funding is confirmed for new wastewater pipes to carry wastewater from homes on The Crescent to the Te Awamutu Wastewater Treatment Plant. Homes on The Crescent were former hospital staff homes and used the old hospital wastewater system which was no longer up to scratch.

2021

February 2021

Government agrees to fund the demolition. Toitū Te Whenua works with Te Arawhiti to agree the terms of the Tokanui Hospital Deferred Selection Process and begins designing project investigations and consultant procurement approach.

11 November 2021

Deed of Settlement signed by Ngāti Maniapoto and the Minister of Waitangi Negotiations. Te Nehenehenui represents Ngāti Maniapoto as the Post Settlement Governance Entity.

2022

Early 2022

Consultants engaged to undertake investigations and support preparations works.

February 2022

New wastewater system and connection installed to service homes on the site.

4 March 2022

Memorandum of Understanding signed between Te Nehenehenui trustees and Toitū Te Whenua.

27 September 2022

The Maniapoto Settlement Claims Act receives royal ascent.

December 2022

Cultural Impact Assessment completed.

2023

May 2023

Refined demolition waste management options assessment and horizontal infrastructure assessment options reports complete.

June 2023

Consultation with iwi on scope of works and waste management options.

August 2023

LINZ reassesses options following consultation based on feedback from Te Nehenehenui and makes recommendation to joint Ministers.

September 2023

Joint Minister’s agree final extent of demolition works.

Last updated