Applications for activity on Crown pastoral land - June 2023 data

Snapshot of Crown pastoral land activity data as at 30 June 2023.

Crown pastoral land activity applications received before 17 November 2022

Applications processed under the Crown Pastoral Land Act 1998 and Land Act 1948.

Application status Total
Received 388
Active 314
Complete 61
Withdrawn* / written approval not needed 13

* Applications have been withdrawn in consultation with Applicants. This may be because they are now permitted activities from 17 November 2022, the activity is already provided for under an existing consent, or the Applicant considers the activity is no longer required.

Application outcome of those completed Total
Granted 46
Granted in part 12
Declined 3

Activity breakdown of active applications

Active applications for June 2023

Crown pastoral land activity applications received from 17 November 2022

Applications processed under the Crown Pastoral Land Reform Act 2022

Application status Total
Received 16
Active 10
Complete 6
Withdrawn* / written approval not needed N/A

Activity breakdown of all applications received from 17 November 2022

Application type Total
Commercial recreation permit 9
Transfer and subleases 4
Easement 2
Discretionary pastoral activity 1

Of those completed

Application status Total
Granted 6
Granted in part N/A
Declined N/A